CITY OF PEORIA 75TH AVENUE WATERLINE: CHOLLA STREET TO THUNDERBIRD ROAD WATER
WATER | WATER LINE | WATER LINE REPLACEMENT
PROJECT OVERVIEW
The City of Peoria replaced aging 8 and 12-inch waterlines with approximately 6,000 feet of new 16-inch waterline along 75th Avenue, between Cholla Street and Thunderbird Road. YPMO was selected to provide PIO services for the 75th Avenue Waterline Construction project in 2021.
Construction was completed in two phases. Phase 1: Cholla Street to Cactus Road, and Phase 2: Bloomfield Road to Thunderbird Road.
YPMO prepared an initial construction notice which was distributed to approximately 900 residents in December 2021. In March 2022, YPMO prepared and distributed a construction update notice for Phase 2 of the project. Two additional construction updates notices were prepared and distributed to the public in July and October to notify of street closures in the area. All construction notices were distributed via email to nearby HOAs and schools.
Throughout construction, YPMO worked closely with the project team to prepare and distribute door hanger notifications for temporary side street closures, as needed, and coordinated water shutoffs for approximately 30 residences.
OWNER
City of Peoria
PROJECT LOCATION
75th Avenue: Cholla Street to Cactus Road
75th Avenue: Bloomfield Road to Thunderbird Road
SERVICES
-Initial Project Notice
-Construction Notice Updates
-Project Hotline
-PI Coordination
PROJECT TEAM